Day 1:

You requested the audit.
Goods to receive:
Our project form gathers high-level information on your code.

Day 2:

Audit Scoping based on a meeting or provided form, checking the availability of auditors.

Day 5-7:

The audit starts with four auditors, and all work independently.
They get a base payment and added bounties per finding.

Day 19-21:

Cross-Validation of all findings with the four auditors and one independent reviewer.
Preliminary report, you improve the code.

Day 28-X:

Final Review of the improved code. Pay less if no high-severity issue is found.